[Urbanstudy] Bangalore-Mysore corridor project runs into trouble again : KSPCB alleges encroachment of tanks, withdraws `consent' for the project
ESG VSNL India
esg at bgl.vsnl.net.in
Fri Oct 6 11:47:31 IST 2006
A very rare but good decision. MoEF is now bound to withdrawn the
Environmental Clearance granted to this project.
If every violator was dealt with at least in this manner, India's
environmental problems could be more than halved.
We now hope the next logical step of initiating criminal action against
NICE (the company implementing the project) for violation of EP Act,
Water and Air Acts, a plethora of other legislations (including Town and
Country Planning Act) and a variety of judgments protecting water
bodies, would follow soon.
There is the issue of needless displacement such gross violations have
caused, both for directly affected farmers and of pastoralists,
downstream farmers, farm labourers, etc. Not to forget the long term
implications of tank destruction, as it completely alters the drainage
pattern and rain water harvesting potential of a watershed in a
semi-arid area.
For more information on how the BMIC project has violated significant
environmental, techno-economic and financial clearance conditions, and
also to review why this project will aid in urban sprawl in Blore,
please visit our website: www.esgindia.org
Leo Saldanha
--
Environment Support Group (R) 105, East End B Main Road Jayanagar 9th
Block East Bangalore 560069. INDIA Tel: 91-80-26341977/26531339 Fax:
91-80-26534364 Email: esg at esgindia.org or esg at bgl.vsnl.net.in Web:
www.esgindia.org
Online edition of India's National Newspaper
Friday, Oct 06, 2006
Front Page <http://www.thehindu.com/2006/10/06/01hdline.htm> Printer
Friendly Page
<http://www.hinduonnet.com/thehindu/thscrip/print.pl?file=2006100619820100.htm&date=2006/10/06/&prd=th&>
Send this Article to a Friend
<http://www.hinduonnet.com/thehindu/thscrip/pgemail.pl?date=2006/10/06/&prd=th&>
* Bangalore-Mysore corridor project runs into trouble again *
Alladi Jayasri
/KSPCB alleges encroachment of tanks, withdraws `consent' for the project /
BANGALORE: The Karnataka State Pollution Control Board (KSPCB) has
withdrawn consent for the 111-km Bangalore-Mysore Infrastructure
Corridor Project, promoted by the Nandi Infrastructure Corridor
Enterprise (NICE), after it found that the road alignment has been
altered in alleged violation of the conditional environmental clearance
granted by the Ministry of Environment and Forests in August 2001.
Over 15 tanks and water bodies, totalling an area of 176 acres, have
been allegedly encroached upon by NICE. The KSPCB issued notice to NICE
last week for these alleged deviations.
Notice issued
KSPCB Chairman H.C. Sharatchandra told /The Hindu/ that a show-cause
notice was issued to NICE three months ago for not fulfilling the
conditions stipulated while granting consent.
To this, the company had said the project was "under various stages of
execution".
Peripheral road
The 41-km peripheral road, starting from Tumkur Road up to Hosur Road,
which crosses important radial roads such as Magadi Road, Mysore Road,
Kanakapura Road, and Bannerghatta Road, was being built in alleged
deviation from the approved alignment at several points, according to
official sources.
Court directives
Sources said there was scope for withdrawing the clearance on the basis
of two directives from the Karnataka High Court.
One of them is the 1995 High Court order on a petition filed by
environmentalist Zafar Futehally, which directed that no tank or water
body in and around Bangalore should be given for any kind of development
project by private or public enterprise.
The second was the more recent order on the petition of another
environmentalist Suresh Heblikar, specifically on Gottigere tank, in
which the direction was to ensure that the natural flow of water into
and out of the tank should not be disturbed by the road, and wherever
needed a flyover should be built.
Road around the tank
The violation here was that the road had instead gone around the tank
periphery, obstructing the natural flow of water.
KSPCB issued a no-objection certificate and consent for establishment
(CFE) to NICE in August 2000 while the MoEF gave conditional clearance
for the project in August 2001.
Fresh affidavit
Officials preparing a fresh affidavit to be submitted to the Supreme
Court shortly said THAT in 2003-04 NICE shifted the alignment drastically.
* The BMIC Area Planning Authority did not share details of the
alignment with the public. Many of the affected persons, whose lands
were acquired, did not even know why they lost their lands until much
later.*
Road opening
Apart from encroaching tanks, NICE could be pulled up by the KSPCB for
assuming that the CFE gave it the right to open the road for use.
This made the opening of the 9.2-km stretch connecting Mysore Road and
Kanakapura Road in June this year, a violation, although it was a minor
transgression, in comparison to what had been done to the tanks, sources
said.
/ /
Printer friendly page
<http://www.hinduonnet.com/thehindu/thscrip/print.pl?file=2006100619820100.htm&date=2006/10/06/&prd=th&>
Send this article to Friends by E-Mail
<http://www.hinduonnet.com/thehindu/thscrip/pgemail.pl?date=2006/10/06/&prd=th&>
------------------------------------------------------------------------
------------------------------------------------------------------------
Front Page <http://www.thehindu.com/2006/10/06/01hdline.htm>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/gif
Size: 3057 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0002.gif
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/png
Size: 147 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0004.png
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/png
Size: 232 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0005.png
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 25966 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment.jpe
More information about the Urbanstudygroup
mailing list