A very rare but good decision. MoEF is now bound to withdrawn the 
Environmental Clearance granted to this project.

If every violator was dealt with at least in this manner, India's 
environmental problems could be more than halved.

We now hope the next logical step of initiating criminal action against 
NICE (the company implementing the project) for violation of EP Act, 
Water and Air Acts, a plethora of other legislations (including Town and 
Country Planning Act) and a variety of judgments protecting water 
bodies, would follow soon.

There is the issue of needless displacement such gross violations have 
caused, both for directly affected farmers and of pastoralists, 
downstream farmers, farm labourers, etc. Not to forget the long term 
implications of tank destruction, as it completely alters the drainage 
pattern and rain water harvesting potential of a watershed in a 
semi-arid area.

For more information on how the BMIC project has violated significant 
environmental, techno-economic and financial clearance conditions, and 
also to review why this project will aid in urban sprawl in Blore, 
please visit our website: www.esgindia.org

Leo Saldanha

-- 

Environment Support Group (R) 105, East End B Main Road Jayanagar 9th 
Block East Bangalore 560069. INDIA Tel: 91-80-26341977/26531339 Fax: 
91-80-26534364 Email: esg at esgindia.org or esg at bgl.vsnl.net.in Web: 
www.esgindia.org


Online edition of India's National Newspaper
Friday, Oct 06, 2006

Front Page <http://www.thehindu.com/2006/10/06/01hdline.htm> Printer 
Friendly Page 
<http://www.hinduonnet.com/thehindu/thscrip/print.pl?file=2006100619820100.htm&date=2006/10/06/&prd=th&>   
Send this Article to a Friend 
<http://www.hinduonnet.com/thehindu/thscrip/pgemail.pl?date=2006/10/06/&prd=th&>

* Bangalore-Mysore corridor project runs into trouble again *

Alladi Jayasri

/KSPCB alleges encroachment of tanks, withdraws `consent' for the project /


BANGALORE: The Karnataka State Pollution Control Board (KSPCB) has 
withdrawn consent for the 111-km Bangalore-Mysore Infrastructure 
Corridor Project, promoted by the Nandi Infrastructure Corridor 
Enterprise (NICE), after it found that the road alignment has been 
altered in alleged violation of the conditional environmental clearance 
granted by the Ministry of Environment and Forests in August 2001.

Over 15 tanks and water bodies, totalling an area of 176 acres, have 
been allegedly encroached upon by NICE. The KSPCB issued notice to NICE 
last week for these alleged deviations.

Notice issued

KSPCB Chairman H.C. Sharatchandra told /The Hindu/ that a show-cause 
notice was issued to NICE three months ago for not fulfilling the 
conditions stipulated while granting consent.

To this, the company had said the project was "under various stages of 
execution".

Peripheral road

The 41-km peripheral road, starting from Tumkur Road up to Hosur Road, 
which crosses important radial roads such as Magadi Road, Mysore Road, 
Kanakapura Road, and Bannerghatta Road, was being built in alleged 
deviation from the approved alignment at several points, according to 
official sources.

Court directives

Sources said there was scope for withdrawing the clearance on the basis 
of two directives from the Karnataka High Court.

One of them is the 1995 High Court order on a petition filed by 
environmentalist Zafar Futehally, which directed that no tank or water 
body in and around Bangalore should be given for any kind of development 
project by private or public enterprise.

The second was the more recent order on the petition of another 
environmentalist Suresh Heblikar, specifically on Gottigere tank, in 
which the direction was to ensure that the natural flow of water into 
and out of the tank should not be disturbed by the road, and wherever 
needed a flyover should be built.

Road around the tank

The violation here was that the road had instead gone around the tank 
periphery, obstructing the natural flow of water.

KSPCB issued a no-objection certificate and consent for establishment 
(CFE) to NICE in August 2000 while the MoEF gave conditional clearance 
for the project in August 2001.

Fresh affidavit

Officials preparing a fresh affidavit to be submitted to the Supreme 
Court shortly said THAT in 2003-04 NICE shifted the alignment drastically.

* The BMIC Area Planning Authority did not share details of the 
alignment with the public. Many of the affected persons, whose lands 
were acquired, did not even know why they lost their lands until much 
later.*

Road opening

Apart from encroaching tanks, NICE could be pulled up by the KSPCB for 
assuming that the CFE gave it the right to open the road for use.

This made the opening of the 9.2-km stretch connecting Mysore Road and 
Kanakapura Road in June this year, a violation, although it was a minor 
transgression, in comparison to what had been done to the tanks, sources 
said.

/ /

Printer friendly page 
<http://www.hinduonnet.com/thehindu/thscrip/print.pl?file=2006100619820100.htm&date=2006/10/06/&prd=th&>   

Send this article to Friends by E-Mail 
<http://www.hinduonnet.com/thehindu/thscrip/pgemail.pl?date=2006/10/06/&prd=th&> 


------------------------------------------------------------------------
------------------------------------------------------------------------

Front Page <http://www.thehindu.com/2006/10/06/01hdline.htm>



-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment.html 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/gif
Size: 3057 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0002.gif 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/png
Size: 147 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0004.png 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/png
Size: 232 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment-0005.png 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: image/jpeg
Size: 25966 bytes
Desc: not available
Url : http://mail.sarai.net/pipermail/urbanstudygroup/attachments/20061006/8e9e7478/attachment.jpe 


More information about the Urbanstudygroup mailing list